Terms and Definitions
Authorization For Expenditure (AFE)
For earned value management to be successful, a request for authorization for expenditure should include a proposed plan with definitions of scope, cost, and schedule, plus a change control process for managing the same. The accuracy and level of detail in the proposed plan should seek to minimize the risk of ambiguity in the event that changes are requested. In other words, the definitions and level of detail should make clear whether a requested change is truly a deviation from the authorized plan. An authorization to proceed with the proposed plan is known as the Authorization for Expenditure (AFE).Baseline
The plan associated with the AFE includes, at a minimum, a budget and a timeline. The plan associated with the AFE is the initial baseline.As you will see in the next section below, titled "Change Requests", a project can have one or more baseline schedules subsequent to the initial baseline schedule.
When changes are authorized subsequent to AFE, a new Baseline should be calculated and a revision number should be attached.
At the end of the project, a comparison between the initial Baseline and the last Baseline can be studied to generate ideas for improving future plans.
Date Line
The Date Line is a vertical line on an Earned Value Management diagram that intersects the x-axis at a point that represents the date up to which progress is being measured, calculated, and reported.The Date Line can be earlier than the current date or the same as the current date but it cannot be later than the current date.
Change Requests
Changes to the Baseline Schedule should be subject to the terms and conditions of the change control process as specified in and authorized by the AFE. Changes can be categorized in many ways but in this article, we are concerned with those changes categorized as having an effect on the scope, cost, and/or schedule of the project.Authorized changes in scope, cost, and/or schedule provide a rationale for creating a new version of the Baseline. In other words, The Baseline can change over time in accordance with authorized project changes.
Maintaining traceability between the Baseline and authorized changes is critical for maintaining traceability.
Key Elements of Earned Value Management
There are three key Earned Value Management terms that you need to memorize so that you can interpret Earned Value Management diagrams and easily perform other Earned Value Management calculations. Below, the three terms are color-coded to match the curves in the Earned Value Management diagram below. (See figure 1.)Planned Value (PV)
PV is also known as the Budgeted Cost of Work Scheduled (BCWS) and is represented by the red curve in the diagram below. In simpler terms, PV is the budgeted cost of performing the scope of work scheduled, over time, through the end of the project timeline.Actual Cost (AC)
AC is also known as the Actual Cost of Work Performed (ACWP) and is represented by the green curve in the diagram below. In simpler terms, AC is the actual cost of performing all work, over time, up to the Date Line.Earned Value (EV)
EV is also known as the Budgeted Cost of Work Performed (BCWP) and is represented by the purple curve in the diagram below. In simpler terms, EV is the budgeted cost of work performed, over time, up to the Date Line.Figure 1 |
Calculating EVM Formulas
Calculating earned value management formulas requires knowledge of the key elements of earned value management, skillful management of the project change control process, maintenance of the forecast, and some simple math calculations.Two Key Variances
There are two key variances in EVM; they are Schedule Variance and Cost Variance. Calculating these two key variances is dependent on skillful updates of PV, inclusive of all authorized changes, and on updates of the actual work performed up to and including work performed on the date of the Date Line.Schedule Variance, SV
As project time elapses, the time available to complete budgeted work is consumed. Work may be completed faster or slower than originally scheduled, so EV may be greater than or less than PV.The formula for calculating SV is as follows.
SV = EV - PV
When EV is greater than PV, SV is a positive number and the project is ahead of schedule. When EV is less than PV, SV is a negative number and the project is behind schedule.
A project can be ahead of schedule at some points along the timeline and behind schedule at other points along the timeline. At points along the timeline where the EV curve is above the PV curve, the project is ahead of schedule by that cost amount; and, at point along the timeline where the EV curve is below the PV curve, the project is behind schedule by that cost amount.
A project can be ahead of schedule at some points along the timeline and behind schedule at other points along the timeline. At points along the timeline where the EV curve is above the PV curve, the project is ahead of schedule by that cost amount; and, at point along the timeline where the EV curve is below the PV curve, the project is behind schedule by that cost amount.
Cost Variance, CV
As work is performed, the project accumulates actual costs, and AC may be greater than or less than EV.
The formula for calculating CV is as follows.
The formula for calculating CV is as follows.
CV = EV - AC
When EV is greater than AC, CV is positive and project spending is under budget. When EV is less than AC, CV is negative and project spending is over budget.A project can be under budget at some points along the timeline and over budget at other points along the timeline. At points along the timeline where the EV curve is above the AC curve, the project spending is under budget; and, at points along the timeline where the EV curve is below the AC curve, the project is over budget by that cost amount.
Two Key Performance Indices
Completing calculations of the two indices is dependent on the values of the three key elements of Earned Value Management: PV, AC, and EV.Schedule Performance Index, SPI
The Schedule Performance Index is a number that indicates the project's conformance to the baseline spending schedule. Project spending can outpace the baseline spending schedule, or it can fall short of the baseline spending schedule.The formula for calculating SPI is as follows.
SPI = EV/PV
When SPI is greater than 1, the cost of work performed is greater than the baseline cost of work scheduled, and the project is said to be earning more than it is costing; this is good. When SPI is less than 1, the cost of work performed is less than the baseline cost of work scheduled, and the project is said to be earning less than it is costing; this is bad.Cost Performance Index, CPI
The Cost Performance Index is a number that indicates the conformance to the cost budget. The actual project cost can be greater than the budgeted or less than the budgeted cost up to, and including, the Date Line.
The formula for calculating CPI is as follows.
ETC is the estimated cost to perform all remaining work; it does not include any cost of work that has already been performed.The formula for calculating CPI is as follows.
CPI = EV/AC
When CPI is greater than 1, project spending is under budget; this is usually a good thing. When CPI is less than 1, project spending is over budget; this is usually a bad thing.Two Key Estimates
The next calculations require a skillful estimate of the remaining work.Estimate To Complete, ETC
The formula for calculating ETC is as follows.
ETC = EAC - AC
When a change to the baseline cost and/or time is authorized, ETC must be updated to account for the change.Estimate At Completion
EAC is the sum of all actual costs to date, plus the estimated cost to perform all remaining work.The formula for calculating EAC is as follows.
EAC = AC + ETC
When a change to the baseline cost and/or time is authorized, EAC must be updated to account for the change.Two Final Calculations
Variance At Completion
VAC is a projection of the budget surplus after all project work has been performed.The formula for calculating VAC is as follows.
VAC = BAC - EAC
When a change to the baseline cost and/or time is authorized, VAC must be updated to account for the change.Schedule Slippage
Schedule Slippage is a measure, in units of time, that the schedule slipped beyond, or finished before, the baseline schedule.The formula for calculating schedule slippage is as follows.
Schedule Slippage = Planned Finish Date - Target Date
When a change to the baseline cost and/or time is authorized, EAC must be updated to account for the change.Key Success Factors
The following are the key success factors for applying Earned Value Management (EVM) to a project.Stakeholder Management
- The stakeholder management plan is specified in the project management plan.
- The stakeholder management process is specified in the project management plan.
- All key stakeholders have been identified.
- Key stakeholder requirements have been identified.
- Stakeholder requirements have been validated by key stakeholders.
- The project management plan has been reviewed and accepted by all key stakeholders.
Scope Management
- A scope statement exists. (A scope statement provides boundaries for decomposition activities.)
- The scope is sufficiently decomposed such that the work can be progressed without ambiguity.
- The work required to progress the project is included in the project management plan.
- The work required to update the project management plan is included in the project management plan.
- The work required for project review meetings is included in the project management plan.
- The work required for quality assurance is included in the project management plan.
- The work required to document and communicate project reports is included in the project management plan.
Integration Management
- The integration management plan is specified in the project management plan.
- Organizational roles and responsibilities are specified in the project management plan.
- All external dependencies are identified in the project management plan.
- The project constraints priority (i.e., cost>time>scope) is specified in the project management plan.
- Activities in the execution plan are linked such that work can be progressed without extraordinary re-planning effort.
- such that the plan can be progressed without extraordinary re-planning.
- The project change control process is specified in the project management plan.
- The project change control process is executed in accordance with the change control process.
- Progress updates reflect the actual progress made during project execution.
- Management reserve for costs (i.e., estiate + 3%) and for time (i.e., target date -3 days/ +2 days) is specified in the project management plan.
- The project execution plan complies with all government regulations and company policies.
Communication Management
- The communication plan is included in the project management plan.
- The project management plan specifies the scope, method, and frequency of reporting.
- The project management plan specifies the method and frequency of project reviews.
- Each project review addresses all of the following elements.
- project progress
- project changes
- current status
- look-ahead
- project metrics
- key open issues
- key risks
- key decisions
HR Management
- The HR Plan is included in the project management plan.
- The project management plan specifies the committed availability of each resource for the duration of the execution plan.
- The project management plan specifies the requisite skills of each resource assigned to perform work.
- The execution plan specifies all HR resource assignments necessary to complete each work package.
- The onboarding process is aligned with requisite HR policies, processes, and procedures.
- The HR resources assigned to the project perform at the skill level specified in the HR plan.
Procurement Management
- The procurement plan is specified in the project management plan.
- Applicable procurement processes and procedures are specified in the project management plan.
- Material requirements are specified in the project management plan.
Quality Management
- The quality management plan is specified in the project management plan.
- The quality requirements are specified in the project management plan.
- Acceptance criteria for each work package are specified in the project management plan.
Risk Management
- The risk management plan is specified in the project management plan.
- The risk processing procedure is specified in the project management plan.
- All aspects of the project have been evaluated for the purpose of identifying risks.
- All risks have been processed in accordance with a risk processing procedure.
- A risk tolerance level has been specified in the project management plan.
Cost Management
- A cost management plan is specified in the project management plan.
- The cost budget request includes a risk response reserve (i.e., +/- 5% of the budgeted cost, etc.).
- A method of accrual has been specified for each resource in the work plan.
- The project management plan specifies standard and premium cost rates for all resources.
- The project management plan specifies the method of estimating the cost of each item to be progressed.
- The project management plan includes an estimate of the cost to complete each activity.
Time Management
- The schedule management plan is specified in the project management plan.
- The timeline includes a management reserve (i.e., +/- 3% of the estimated project duration, etc.).
- The frequency of progress plan updates is specified in the project management plan.
- The project start date is defined in the project plan.
- The project plan specifies all regular working and non-working days throughout the duration of the project timeline.
- The project management plan specifies the method of estimating the time required to complete each item to be progressed.
- The project management plan includes an estimate of the time required to complete each activity.
This is really good info. Very detailed and well thought out.
ReplyDeleteThank you.! I plan to post more from time to time. Feedback and thoughts about your own experiences is always appreciated.
Delete